Progress So Far October 2002
- Site clearance, demolition and preparation of site completed.
- Boundary walls to South, North and East elevation part complete.
- Inner shrines for Sri Ganapathi, Sri Murugan and Sri Shiva
completed to roof.
- Work underway on foundation for Rajagopuram and whole building
structure due to complete in December 2002.
- Granite carvings for Rajagopuram and Vinanams kast shipment
expected in January 2003.
- Designs completed for Temple and Communal facilities.
- Tendering for major works contract to be underway in December,
- Costs incurred so far £0.5m
|