Progress So Far October 2002   
  • Site clearance, demolition and preparation of site completed.
  • Boundary walls to South, North and East elevation part complete.
  • Inner shrines for Sri Ganapathi, Sri Murugan and Sri Shiva completed to roof.
  • Work underway on foundation for Rajagopuram and whole building structure due to complete in December 2002.
  • Granite carvings for Rajagopuram and Vinanams kast shipment expected in January 2003.
  • Designs completed for Temple and Communal facilities.
  • Tendering for major works contract to be underway in December,
  • Costs incurred so far £0.5m            